Query on a preprocessed total

Meeting place for R&R customers and clients to share tips and ideas. Post your questions, messages or problems here.
Post Reply
MIke_Csom_(Guest)
Posts: 47
Joined: Tue Oct 10, 2017 12:44 pm

Query on a preprocessed total

Post by MIke_Csom_(Guest) » Wed Dec 22, 2004 11:59 am

Can you query on a preprocessed total field? I am totaling hours worked and only want the show work done on files where hours is less than 10.____Thanks in advance,____Mike

kfleming
Posts: 5795
Joined: Tue Oct 10, 2017 12:44 pm

=> RE: Query on a preprocessed total

Post by kfleming » Fri Dec 24, 2004 8:07 am

As long as that total is at the highest level in the report, it should be available for use in a query.____Kathleen__R&R Support