Page 1 of 1

Scope with Calculate field

Posted: Fri Oct 01, 2004 12:21 am
by Moah_(Guest)
How can I put the Start Value in Scope with Calculate field?____Thanks,__Moah__

=> RE: Scope with Calculate field

Posted: Sat Oct 02, 2004 11:38 am
by kfleming
In V10+ you can select a parameteRR field as a scope value.____Kathleen__R&R Support

==> RE: Scope with Calculate field

Posted: Mon Oct 04, 2004 6:52 am
by Moah_(Guest)
Do you mean RI_LOSCOPE & RI_HISCOPE?__Thanks in advance,__Moah

===> RE: Scope with Calculate field

Posted: Mon Oct 04, 2004 7:20 am
by kfleming
You would need to save the parameteRR field as the scope end point inside of the report. Then at runtime you would be prompted to enter the scope values. It cannot currently be done via control file scope settings.____Kathleen__R&R Support