Scope with Calculate field
-
- Posts: 2
- Joined: Tue Oct 10, 2017 12:44 pm
Scope with Calculate field
How can I put the Start Value in Scope with Calculate field?____Thanks,__Moah__
=> RE: Scope with Calculate field
In V10+ you can select a parameteRR field as a scope value.____Kathleen__R&R Support
-
- Posts: 2
- Joined: Tue Oct 10, 2017 12:44 pm
==> RE: Scope with Calculate field
Do you mean RI_LOSCOPE & RI_HISCOPE?__Thanks in advance,__Moah
===> RE: Scope with Calculate field
You would need to save the parameteRR field as the scope end point inside of the report. Then at runtime you would be prompted to enter the scope values. It cannot currently be done via control file scope settings.____Kathleen__R&R Support